Canal Covering in Luxor

The project involved the installation of 2,000 linear meters of concrete pipelines and culverts with a diameter of 2.5 meters. Its objective was to replace an open canal in Luxor with a covered canal within the same lane. Undertaking this project required meticulous planning and monitoring by the company's dedicated team to accommodate irrigation shifts, which allowed for a maximum working period of five days per canal. Timely completion necessitated precise coordination with different equipment and the use of advanced rapid drying methods.